Woodlawn Reconstruction

The reconstruction of Woodlawn Blvd. between Madison Ave. and English St. will begin Monday, June 3, 2019. 

The initial phase will reconstruct Woodlawn Blvd. from Madison Ave. to Market St. including the intersection of Market and Woodlawn. This portion of Woodlawn will be closed entirely during construction, although sidewalks will generally remain open. Completion is anticipated by July 2.

The second phase, from Market St. to English St., will begin following phase one. Woodlawn Blvd. will be one-way northbound during this time. While intersections will be closed periodically for construction, access will be maintained to adjacent properties. Weather permitting, all phases of construction should be completed before school starts in August.

If you have questions, contact Assistant City Engineer Ky Louanghaksaphone, P.E., at 316-788-6632 x1255. Updates during the project as progress occurs will be posted to Facebook (Derby, Kansas City Hall) and Twitter (@DerbyKS).  